Chippewa Campground Wastewater Project

Project year: 2011

Olynick’s were the general contractors. Job consisted of all site preparation (using backhoes, dozers, loaders, gravel trucks, etc.), sludge removal from old lagoon, lagoon abandonment, buildings demolition, water system upgrades, erosion control, etc. Olynick’s supervised all sub-contractors for the installation of electrical work, sewer pipe installation, building construction, and water line installation.